Dewey Street - 2018

A complete reconstruction of Dewey Street from South 10th Street to South 26th Street will be done in the Summer of 2018.

The contractor for the reconstruction work is Vinton Construction Company.  The project includes pavement removal, grading, graveling, fine grading, doweled concrete pavement with integral curb, concrete driveways and spot replacement of concrete sidewalks.  The project also includes replacing some storm sewer manholes, inlets and inlet leads, installing underdrains, replacing some sanitary manhole structures, resurfacing of block sanitary manholes, sanitary building sewers, water services, lawn restoration, pavement markings, tree removal and tree planting.

If you have any questions pertaining to this project, please contact the Engineering Department at (920) 686-6910.


ANTICIPATED START DATE:  JULY 2, 2018

CONTRACT COMPLETION DATE:  OCTOBER 31, 2018

Vinton Construction will also be replacing the watermain for the Manitowoc Public Utilities.

Michels Pipeline Services is currently working on re-lining the mainline sanitary sewer from South 10th to South 18th Street.  This completion date will be around June 1st, 2018.

A meeting will be held with the contractor and property owners prior to the start of construction.  A letter will be mailed out once the meeting date and time have been determined.

  1. Contacts


    GREG MINIKEL, P.E.
    PROJECT MANAGER
    (920) 686-6910
    (920) 374-0411

    EMAIL
    STEVE HERZOG
    PROJECT INSPECTO
    R
    (920) 686-6910